ENGINEERING DEPARTMENT

 

  Overview of the New Zone — Engineering Perspective

South Coast Railway is the newly formed 18th zone of the Indian Railways with its Headquarters office at Visakhapatnam. It has been created duly carving out 3 Divisions of South Central Railway namely Vijayawada, Guntur, Guntakal and by adding the truncated part of existing WAT division of ECoR and that portion of KUR division of ECoR falling within geographical boundary of Andhra Pradesh, duly renaming as Visakhapatnam Division.

97.75% track of SCoR jurisdiction falls within the state of Andhra Pradesh. Remaining 2.25% of the Route Km is spread over adjacent states (Telangana, Karnataka and Tamil Nadu). It has 3532.407 Route Km and 6455.436 Track Kms on Group A, B and D routes. This zone has 1472 Km of 130 Kmph running track (i.e. 41.7% of total Route Km).

There are 385 Railway Stations including 02 numbers of NSG1 Stations (VSKP, BZA). SCoR Rail Network serves four Freight handling ports — Visakhapatnam, Gangavaram, Krishnapatnam and Kakinada.

There are 13,512 Bridges over SCoR network. Out of them 36 are Important Bridges which include the Godavari Bridges (Road-cum-Rail bridge, Bowstring Arch bridge) at Rajahmundry, & Krishna Bridge at Vijayawada along with 1101 Major Bridges and 12,351 Minor Bridges. The Godavari rail bridges in Rajahmundry are engineering marvels — they include the historic Havelock bridge (de-commissioned), the Godavari Arch Bridge (a bowstring arch rail bridge) and the Godavari Bridge, one of Asia’s longest continuous Road-cum-Rail Bridges, with a length of 2.79 Km on river Godavari. SCoR track network also consists of the 6.6 Km longest tunnel in the Krishnapatnam – Obulavaripalli line.

                         

We have a Track Machine Workshop at Rayanapadu with in-house POH facility caters to the track machine needs of SCoR, SCR, ECoR, SWR and SR.

We, the Engineering branch of SCoRly maintain the safety of track, yard layouts and bridges. We also maintain station buildings, passenger amenities and other service buildings right from Ichapuram in East to Haddinagundu near Ballary in West, Motumarri in North to Bommasamudram in South.  S Co Rly track follows entire Circar coast (Ichapuram to Kakinada) and Coromandel Coast (Kakinada to Gudur) connecting the ports to the hinterland., for a length of 896Km on the coast.

South Coast Railways’ Engineering Department owns the responsibility of continuous improvement, maintenance and safeguard of all permanent assets spread over its jurisdiction.

Scheduled inspections and systematic preventive maintenance of permanent way as well as of major/important bridges and strengthening of infrastructure are given high priority to reduce service interruptions and to improve the long-term performance of civil engineering assets. In addition to, the department manages railway land, water supply & drainage networks, station/passenger amenities, contributing towards smooth trains operations as well as better customer interaction experience

Construction wing of SCoR shoulders the responsibility of implementing new infrastructure development works with in the jurisdictions of SCoR such as planning, survey and construction of new lines, doubling and multi tracking of existing tracks, stations’ development, line capacity improvements, yard modernization projects etc., Engineering department is responsible for carrying out all these activities within the prescribed engineering specifications, duly ensuring the safety of running trains to achieve the targets.

Construction wing of S Co Rly has vowed to adopt advanced construction techniques and environment friendly maintenance practices thus supporting sustainable development of the railway system. Through continuous innovation, assessment and coordination with other branches, the Team Engineering helps in reliability, safety and future readiness of the South Coast Railway network.

  Main Engineering Features of SCoR

1.  State-wise Route Length of Rail Network

The major Route Km (97.75%) passes through Andhra Pradesh followed by Karnataka, Telangana and Tamil Nadu.

S.N

State

Route Km

%

1

Andhra Pradesh

3453.00

97.75

2

Karnataka

47.03

1.34

3

Telangana

25.51

0.72

4

Tamilnadu

6.86

0.19

 

Total

3532.407

100.00

 

2.  Division-wise Route Km and Track Km

The major Route Km passes through Guntakal Division, followed by Vijayawada, Guntur and Visakhapatnam Division.

S.N

Division

Route Km

%

Track Km

1

Visakhapatnam

460.767

12.89

979.546

2

Vijayawada

1111.114

31.10

2409.05

3

Guntur

613.710

17.18

883.50

4

Guntakal

1346.82

38.81

2183.33

 

Total

3532.407

 

6455.43

 

3.  Group-wise Classification (in Km)

SCoR has major portion of Group B Route, followed by Group D and Group A.

S.N

Division

Group A

Group B

Group D

Total

1

VSKP

—

266.458

194.309

460.767

2

BZA

355.960

498.358

256.796

1111.114

3

GNT

—

415.480

198.231

613.711

4

GTL

—

908.360

438.455

1346.815

 

TOTAL

355.960

2088.656

1087.791

3532.407

 

4.  List of Bridges

There are 13,512 Bridges in SCoR. Details are as follows:

SN

Division

Important (Mega)

Major

Minor

Total

1

VSKP

4

187

2698

2889

2

BZA

11

400

4152

4563

3

GNT

3

147

1207

1357

4

GTL

18

370

4315

4703

 

Total

36

1101

12351

13512

 

The longest bridge (2789 m length) is on River Godavari at Rajahmundry.

 

  Key Achievements

SCoR will be operational from 01.06.2026. Achievements of SCoR will be updated from 01.06.2026.

 

  Current Assignments

Ongoing projects, specifically those involving infrastructure setup targeted in FY 2026-27:

Targeted Works — Open Line

S.No

Name of the Work

Unit

Target 2026-27

1

CTR

Km

534.11

2

TRR(P)

Km

511.77

3(i)

Deep Screening Plain Track

Km

447.55

3(ii)

Deep Screening of Turnouts

Nos

370

4(i)

LC Elimination — RUB/LHS

Nos

32

4(ii)

LC Elimination — ROBs

Nos

1

5(i)

Speed Enhancement up to 130 Kmph

Km

161.26

5(ii)

Speed Enhancement up to 110 Kmph

Km

180.18

 

Targeted Works — Construction Organisation (Track Length in Km)

S.No

Name of Project

Block Section

Target 2026-27

1

3rd and 4th Line between VSKP and GPT

3rd and 4th line b/w VSKP-GPT

12.04

2

SCMN North and GPT Yard Remodelling for removal of diamond crossing

SCMN Yard Re-Modelling

3.00

3

4th Line between Kothavalasa – Vizianagaram

KTV-KPL

7.749

4

VZM-TIG 3rd Line

3rd Line: DNV-GTLM

35.76

5

VZM-NML Bypass

8.63

6

VZM-GTLM

5.65

7

Nadikudi – Srikalahaasti NL

NL: Kanigiri-Pamuru

24.00

8

Bye Pass at BZA

Bypass (Gunadala-Mustabad)

6.55

9

GNT-GTL Doubling

Doubling (GZL-NDL)

15.00

10

Bypass at BZA

Bypass (Rayanapadu-BZA N Cabin)

10.03

11

Gooty-Pendakal Doubling

Doubling (PDL-RMPL)

9.60

12

RMPL-GY

19.62

13

Bypass RU, GY, WD

RU Bypass

1.50

 

TOTAL

 

159.129 Km

Source : South Coast Railway Last Reviewed : 22-06-2026